Project title: Tomball Parking Lot

Project Owner: City of Tomball

Service: Construction Services

Market(s): Public Facilities Transportation

Project Scope: Project scope of work included Site clearing, SWPPP, Temporary Asphalt, removal of road pavement and associated drainage, over 1,000' of storm system (12-24" RCP, MH, Inlets), Underground detention, 5,000 SY concrete pavement over 2" of HMAC and black base, curb & Gutter, site lighting, signage, stripping, rail road fence, and final clean up/close out.

Project Start: Oct 2012

Project End: Jan 2013

Project Manager: Jovanni Castilla

Project Budget: $680K